Lobby Refurbishment – Schedule

Fort Dunlop is set to undergo a series of developments this year which will see the landmark building up its game as both a place to work and a leisure destination.

Work has now started on the refurbishment of the reception area. See the schedule of works below. Please note that dates are subject to change.

This page will be regularly updated should there be any changes but you can find all the latest information on Twitter or sign up for our newsletter over to your left.

We apologise for any inconvenience the construction works may cause, but please bear with us while we make your building a better place to be.

Please email fortdunlop@capitalpropertiesltd.com or tweet us if you have any questions.

Start Duration Finish
EXTERNAL WORKS
Construct external walls 18th May 2015 3 weeks 5th June 2015
External glazing 8th June 2015 2 weeks 19th June 2015
Entrance door installation 22nd June 2015 1 week 26th June 2015

INTERNAL WORKS
M & E make safe / temp supplies 13th April 2015 3 days 15th April 2015
Installation temporary screens 13th April 2015 1 week 17th April 2015
Strip out works 13th April 2015 2 weeks 24th April 2015
Electrical 1st fix 20th April 2015 4 weeks 15th May 2015
Electrical BWIC 27th April 2015 2 weeks 8th May 2015
Form new openings 27th April 2015 2 weeks 8th May 2015
Order specialist lighting 27th April 2015 5 weeks 29th May 2015
Specialist joinery manufacturer 4th May 2015 6 weeks 12th June 2015
Loose furniture manufacturer 4th May 2015 8 weeks 26th June 2015
Steelwork installation 11th May 2015 2 weeks 22nd June 2015
Making good walls & plaster 11th May 2015 2 weeks 22nd June 2015
Electrical 2nd fix 18th May 2015 4 weeks 12th June 2015
Fire alarm system installation 25th May 2015 2 weeks 5th June 2015
CCTV installation 25th May 2015 2 weeks 5th June 2015
Suspended ceiling 1st June 2015 2 weeks 12th June 2015
Timber ceilings 1st June 2015 2 weeks 12th June 2015
Tape & fill 8th June 2015 1 week 12th June 2015
Decorations 15th June 2015 2 weeks 26th June 2015
Tiled flooring 15th June 2015 2 weeks 26th June 2015
Specialist joinery installation 15th June 2015 2 weeks 26th June 2015
Vinyl flooring 22nd June 2015 1 week 26th June
Loose furniture installation 29th June 2015 1 week 3rd July 2015
Commission 29th June 2015 1 week 3rd July 2015
Clean 2nd July 2015 2 days 3rd July 2015
Tennant fit out works 6th July 2015 2 weeks 17th July 2015

COMPLETION
Late August